CONSTRUCTION OF THE TEMPORARY ELEMENTARY SCHOOL “VAT BUSHI” IN LALËZ
Location: Lalëz, Durrës / Albania
Duration: 2021 (45 days)
Client: Albanian Development Fund funded by KfW
Scope: Construction of interim elementary consisting in steel structure containers and sandwich panels
Type of Contract: Turnkey, Construction
The temporary “Vat Bushi” School was constructed with container units featuring a metal structure and sandwich panels as an addition to an existing building to accommodate students from the school, which was damaged by the 2019 earthquake.
The challenge of this project was the short construction timeframe (only 45 days) to ensure the school was ready for the start of the new academic year.